Planning Tank Delivery and Access

Before a tank or its panels arrive on site, a detailed access survey must cover every point on the delivery route: doorway widths, staircases, elevators, corridor turns, ceiling heights, and any crane access points.

  • One-piece tanks must physically fit through all openings. If a large one-piece tank cannot pass through the narrowest constraint, either a smaller one-piece must be selected, a sectional tank specified instead, or temporary structural modifications (partial wall removal, roof cranage) planned and costed.
  • Sectional GRP panels can pass through doorways of 750 mm minimum clear width. All doorways, stairwells, corridors, and lifts on the delivery route must be surveyed and confirmed before specifying panel dimensions. A tank that cannot be delivered to the plant room in its required configuration cannot be installed.
  • The tank top must also accommodate the access provisions required for confined space entry — manway clearance, tripod rescue system height, and platform space.

oN-SITE HANDLING

Identify requirements for forklifts, pallet jacks, or hoists to move panels from delivery point to installation location. Schedule sufficient manpower — GRP panels are lightweight but still require two people to carry safely. Safety considerations for crew working at height or in confined spaces should be integrated into the method statement.

Structural Loading and Floor Loading Implications

Water weighs 1 kg per litre (1,000 kg per m³). A fully charged 10,000 L tank exerts 10 tonnes of load on the plant room floor, distributed over the tank base footprint.

Structural assessment of the floor is required for any tank above approximately 5,000 L in an existing building, and should be confirmed at design stage for new builds. Distributed loading across the tank base does not eliminate the need for a structural check – slab capacity and point load at supports must both be assessed.

CONSEQUENCE OF NON-COMPLIANCE

BASE SUPPORT REQUIREMENTS

For EFB sectional tanks, the support system typically comprises parallel concrete plinths or rolled steel joists (RSJs) at 1,000 mm centres for metric panels or 1,220 mm centres for imperial panels. The supports should run in one direction only and must be at least 300 mm longer than the overall length of the tank to support the external vertical flanges.

INSTALLATION REQUIREMENT

FINAL BASE SUPPORT SYSTEM

The final base support system must be flat, level, and strong enough to support the weight of the tank when full without movement. For IFB or TIF tanks placed on a solid slab, the slab must be reinforced to bear the full water load plus the self-weight of the tank.

Base Preparation and Levelness Tolerances

A level base is fundamental for the structural integrity of a water tank. An uneven foundation causes stress on the tank walls, leading to cracks and leaks over time. Industry-standard tolerances for sectional tank bases are:

  • 2 mm in any metre
  • 6 mm in any 6 metres
  • Maximum beam deflection 1:500

Achieving these tolerances requires precision during construction. Use a laser level to verify flatness before tank assembly. Where steel beams are used, shims or self-levelling grout may be needed to bring supports within tolerance. 

BASE MATERIALS

Use durable, water-resistant materials that can withstand the tank’s weight and environmental conditions. Using materials like chipboard instead of marine-grade plywood can result in moisture absorption, leading to base degradation and potential tank failure. Always opt for materials specified by the tank manufacturer — typically concrete plinths, steel beams, or marine-grade board.

FINAL NOTE

Clean the base of any local debris or other items before placing the tank, as foreign objects can create pressure points and damage the tank base over time.

Common Installation Mistakes and How to Avoid Them

The following nine failure modes are regularly encountered in water tank installations:

Uneven Base Installation

A level base is fundamental. An uneven foundation causes stress on tank walls, leading to cracks and leaks.

fix

Ensure the base is constructed using appropriate materials like base levelling steels and is perfectly level before installation.

Using Inappropriate Base Materials

Using chipboard instead of marine-grade plywood can result in moisture absorption, leading to base degradation and tank failure.

fix

Always opt for durable, water-resistant materials.

Oversized Tanks Leading to Stagnation

An oversized tank leads to water stagnation due to insufficient turnover. Stagnant water becomes a breeding ground for bacteria, including Legionella, posing health risks and compliance issues.

fix

Assess facility water usage accurately to determine the appropriate tank size.

Inadequate Access for Maintenance

Installing tanks in locations with limited access hinders routine inspections, cleaning, and maintenance, leading to neglected upkeep and potential system failures.

fix

Ensure the tank’s placement allows for easy and safe access for personnel.

Improper Bolt Tightening

Bolts not adequately tightened during installation can loosen over time, leading to leaks and structural instability.

fix

Follow manufacturer specifications for bolt torque and recheck tightness after the tank has been filled and settled.

Using Non-Marine-Grade Bolts and Washers

Standard bolts and washers instead of marine-grade options lead to rapid corrosion, especially in humid environments. Corroded fittings compromise the tank’s integrity.

fix

Always use corrosion-resistant, marine-grade hardware.

Inadequate or Poorly Installed Seals

Low-quality sealants or improper installation techniques result in seal failure.

fix

Ensure that high-quality, WRAS-approved sealants are used and that installation follows best practices to maintain watertight integrity.

Neglecting Tie Bar Tension

Tie bars are essential for maintaining structural integrity of sectional water tanks. If not properly tensioned, tank walls can bow or flex when filled, leading to joint stress and potential leaks.

fix

Regularly check and adjust tie bar tension as part of installation and maintenance.

Using Non-WRAS Approved Materials

Materials that are not WRAS approved can lead to compliance issues and potential contamination of the water supply.

fix

Ensure all materials, including sealants, coatings, and fittings, meet WRAS standards.

Pre-installation recommendation

Run this list past the chosen contractor and ask them to verify their plans in respect to each point, providing confidence that the installation will not suffer from one or more of these issues.

Frequently asked questions

What should be checked before installing a water storage tank?

Before installing a water storage tank, the full delivery route should be checked, including doorway widths, staircases, corridors, lifts, ceiling heights, and crane access points.

The installation area should also be reviewed for structural loading, floor strength, base levelness, support design, maintenance access, and safe working requirements. These checks help confirm that the tank can be delivered, positioned, filled, maintained, and operated safely.

Structural loading is important because water is heavy. A full water tank places a significant load on the floor, support beams, plinths, or slab beneath it.

As a simple guide, water weighs 1 kg per litre, so a 10,000-litre water tank holds approximately 10 tonnes of water before allowing for the weight of the tank itself. The floor structure should therefore be assessed before installation, especially for larger tanks or installations in existing buildings.

A sectional water tank requires a flat, level, and load-bearing base that can support the full tank weight when filled. Depending on the tank type, this may involve concrete plinths, rolled steel joists, a reinforced slab, or another manufacturer-approved support system.

Base levelness is critical. An uneven base can place stress on the tank panels, joints, seals, and fixings, increasing the risk of leaks, panel distortion, or premature failure.

Common water tank installation mistakes include poor access planning, uneven base preparation, incorrect support spacing, inadequate maintenance clearance, poor bolt tightening, unsuitable fixings, low-quality seals, and the use of non-approved materials.

These issues can lead to leaks, structural movement, corrosion, hygiene risks, or early tank failure. A pre-installation review with the contractor can help confirm that access, base preparation, structural support, and assembly requirements have been properly planned.

Access space depends on the tank type, base configuration, and maintenance requirements, but the tank should always be installed with enough clearance for inspection, cleaning, valve access, and safe future servicing.

For sectional tanks, access planning is especially important. EFB tanks usually require clearance around the tank and below the base for external flange assembly, while IFB and TIF tanks can be better suited to restricted spaces. The required access should be confirmed with the tank manufacturer before the plant room layout is finalised.

CONTENTS

Free Download

Complete GRP Cold Water Tank Guide

Full lifecycle coverage — sizing, compliance, installation, Legionella control, and O&M schedules.

RELATED TECHNICAL GUIDES

GO DEEPER ON THE TOPICS THAT MATTER

Each article in this series covers a specific aspect of cold water storage in multi-storey buildings at full technical depth, with compliance references, worked examples, and checklists.

infrastructure

Sectional GRP Cold Water Tanks in UK Infrastructure Projects

A technical reference covering material selection, regulatory obligations, capacity calculation, installation, and maintenance across commercial, healthcare, data centre, and high-rise applications.

MATERIAL

GRP vs Steel vs Concrete Water Tanks (Material Comparison)

Compare GRP (fibreglass) vs steel vs concrete water storage tanks. Covers corrosion resistance, typical lifespan (20–40+ years), structural and installation differences.

CONFIGURATION

Tank Configuration Explained (Sectional vs One-Piece vs Bespoke)

 Understand GRP water tank configurations: sectional (modular panel) tanks vs one-piece (monolithic) tanks, plus bespoke options. Covers dual-compartment and duty-standby.

Sizing

How to Size Cold Water Storage Tanks (Step-by-Step UK Method)

Step-by-step guide to sizing cold water storage tanks in the UK. Covers 24-hour vs 48–72-hour storage philosophies, demand profiles by building type. 

Regulation

GRP Water Tank Compliance – UK Regulations, Standards & Best Practices

Comprehensive UK compliance guide for GRP cold water storage tanks. Covers the Water Supply (Water Fittings) Regulations 1999, Regulation 4.

Maintenance

Maintenance, Legionella Control & Whole-Life Performance

Guide to maintaining cold water storage tanks for long-term performance. Covers routine inspection and cleaning

Free Download

Read the complete technical guide

Published by Tricel Water in April 2026, this whitepaper is a specification and compliance reference for engineers, asset managers, facilities managers, and dutyholders involved in the design, procurement, installation, or maintenance of cold water storage systems in UK commercial and public sector buildings.

This water tank material comparison guide supports early-stage specification and procurement decisions for UK commercial water storage projects.

This guide is provided for general guidance and information purposes only. It does not constitute engineering advice and should not be relied upon as the sole basis for design decisions. © 2026 Tricel Water. All rights reserved.