GRP Hospital Water Storage Tanks at University Hospital Crosshouse, Kilmarnock

Tricel Water supplied and installed two large GRP sectional water storage tanks at University Hospital Crosshouse in Kilmarnock for NHS Ayrshire & Arran. Working within a continuously operating hospital, the project required the existing tanks to be replaced without interrupting the site’s water supply.

Project Details

Entrance sign for University Hospital Crosshouse in Kilmarnock, Scotland, with the hospital building, car park, and NHS Ayrshire & Arran branding visible in the background.

Dimensions

12m × 9m × 9m

No. of Tanks

2

Tank Type

GRP Sectional Cold Water Storage Tanks

Assembly

Assembled on-site

Client

NHS Ayrshire & Arran

Contractor

BBESL Glasgow

Supplier/Installer

Tricel — Nicholson Plastics

Published
Sector

Healthcare & NHS

Location

Kilmarnock, Scotland

Reading Time

Approx. 5 minutes

Summary

University Hospital Crosshouse is a major NHS hospital serving East and North Ayrshire. Replacing cold water storage infrastructure within an operational hospital presented a particular challenge: clinical services had to continue while the existing tanks were removed and the new tanks installed.

NHS Ayrshire & Arran required two GRP sectional cold water storage tanks measuring 12 m × 9 m × 2 m each. Before installation began, the existing tank base was assessed and modifications were identified as necessary to provide appropriate structural support for the replacement tanks.

Tricel’s sales, manufacturing, logistics and site teams coordinated with BBESL Glasgow and the wider project team to manufacture, deliver and assemble the tanks on site. Sectional construction allowed the tank components to be taken to the installation area and assembled in position.

The installation was completed within two weeks without interruption to the hospital’s water supply, while meeting the project’s SHTM 04-01 and potable-water requirements.

Project Information

At a Glance

Client

University Hospital Crosshouse required replacement cold water storage infrastructure while the hospital remained fully operational.

Industry

Healthcare & NHS

Contractor

BBESL Glasgow worked with Tricel’s project teams during the hospital water tank replacement programme.

Tank Specification

Two 12 m × 9 m × 2 m GRP sectional cold water storage tanks. Each tank’s geometric volume is 216,000 litres, giving 432,000 litres across the two tanks. 

Project

Removal of the existing hospital water tanks and installation of two replacement GRP sectional tanks, including assessment and modification of the existing support base.

Challenge

The work had to be carried out inside a continuously operating hospital without disrupting its water supply, while meeting healthcare water-storage requirements.

Timeline

July 2021 — Water storage tank replacement project completed

Two-week installation programme

Current Project Status

The replacement GRP sectional tanks were installed and brought into service, providing the hospital with compliant cold water storage infrastructure without an interruption to water supply.

Project Background

Water Tank Replacement Within a Live NHS Hospital

University Hospital Crosshouse is a large district general hospital near Kilmarnock operated by NHS Ayrshire & Arran. NHS 24 currently describes the hospital as providing a wide range of services, including paediatric inpatient services, and as the location of the Emergency Department serving East and North Ayrshire. 

The hospital required its existing cold water storage tanks to be removed and replaced with new GRP sectional tanks.

Unlike a conventional commercial installation, the work was being undertaken within an operational healthcare environment. Water availability had to be maintained throughout the project because hospital clinical services, catering, infection-control activities and other essential functions depend on a continuous water supply. Tricel’s current NHS water-resilience guide specifically identifies zero supply interruption as a requirement of the Crosshouse project. 

Two GRP sectional tanks measuring 12 m × 9 m × 2 m were selected for the replacement installation.

Before the new tanks could be installed, the existing foundation was inspected to establish whether it could adequately support the replacement system. The inspection identified that modifications were required before tank assembly could proceed.

Delivery Approach

Tricel's Engineering and Delivery Approach

Completing a major cold water storage replacement within a live hospital required planning across structural preparation, manufacturing, delivery, assembly and commissioning.

Main entrance of University Hospital Crosshouse featuring the Ralf entrance, landscaped grounds, access road, and multi-storey hospital building under a clear sky.

Pre-Installation Foundation Assessment

Before the replacement tanks were installed, Tricel’s installation team assessed the existing supporting foundation.

The inspection identified modifications that were required before the base could safely support the new GRP sectional tanks. Completing this work before tank assembly reduced the risk of structural issues affecting the installation programme.

Sectional Tank Construction

The replacement tanks were supplied in sectional GRP form.

Individual panels could therefore be transported to the tank location and assembled in situ rather than requiring complete tanks to be lifted into the building.

Tricel’s NHS water-resilience guide notes that this method avoided the need for large-scale crane lifting or major structural opening works that could have created additional disruption within the hospital.

Working With the Hospital Contractor

Tricel worked alongside BBESL Glasgow, the project contractor.

Coordination between the contractor and Tricel’s internal teams covered preparation of the tank base, delivery and installation requirements, helping the project remain within programme while hospital operations continued.

Maintaining the Hospital Water Supply

One of the principal project requirements was that installation work could not disrupt the hospital’s water supply.

The replacement programme was therefore planned around maintaining continuous water availability throughout the works.

The completed project recorded zero disruption to water supply.

Time-Critical Delivery

The client required guaranteed readiness ahead of the major stadium event scheduled for 5 November 2025.

Both tanks were successfully installed ahead of deadline.

The Brief

Understanding the Challenge

The University Hospital Crosshouse water storage replacement presented four principal challenges.

•Live Hospital Environment: The project was taking place within an operational NHS hospital where clinical and support services had to continue throughout the works.

•Zero Water-Supply Interruption: The existing tanks had to be replaced without interrupting water availability to the hospital.

•Existing Foundation Condition: A pre-installation assessment found that the existing tank base required modification before the new GRP tanks could be installed.

•Healthcare Compliance: The replacement water-storage installation had to meet the applicable healthcare and potable-water requirements, including SHTM 04-01 and WRAS requirements.

Programme

Timeline

JULY 2021

Tricel supplied and installed two 12 m × 9 m × 2 m GRP sectional cold water storage tanks at University Hospital Crosshouse.

TWO-WEEK INSTALLATION

Live-Site Replacement Completed. The programme included preparation of the existing foundation, delivery of the sectional components and assembly of the replacement tanks while maintaining the hospital’s water supply.

NOW

The completed installation provides GRP cold water storage infrastructure for University Hospital Crosshouse as part of NHS Ayrshire & Arran’s healthcare estate.

Outcome

A Hospital Water Storage Upgrade Delivered Without Supply Disruption

ZERO DISRUPTION

The tank replacement was completed without interruption to the hospital’s water supply.

TWO WEEKS

The installation programme was completed within a two-week period.

TWO GRP TANKS

Two 12 m × 9 m × 2 m sectional GRP tanks were installed.

432,000 LITRES

The two tanks provide a combined geometric storage volume of approximately 432,000 litres. Tricel’s current healthcare page also describes the Crosshouse installation as 432,000 L combined capacity.

HEALTHCARE COMPLIANCE

The installation was specified against SHTM 04-01 and potable-water requirements.

LIVE-SITE INSTALLATION

Sectional construction allowed the replacement tanks to be assembled at their final location while limiting disruption within the operational hospital.

Common Questions

Frequently Asked Questions

How did Tricel replace the water tanks without disrupting the hospital's water supply?

The installation programme was planned around maintaining continuous water availability throughout the works. Tricel coordinated the preparation, manufacturing, logistics and site installation stages with the project contractor, allowing the replacement to be completed without recorded interruption to the hospital’s water supply.

Sectional tanks can be transported to the installation area as individual components and assembled in situ. For the Crosshouse project, this helped avoid the major lifting or structural opening work that could have caused additional disruption inside the hospital.

Yes. Cold water storage tanks should remain accessible for routine inspection, cleaning and maintenance as required by the building’s water safety procedures. Maintenance requirements should therefore influence the original tank location and surrounding access space.

Useful information includes the required storage capacity, available tank dimensions, plant-room access, inlet and outlet sizes and positions, required compartmentation, insulation requirements, access hatches, internal fittings and any relevant project standards. Drawings and site constraints also help reduce revisions later in the specification process.

Yes. Sectional tanks can be configured with internal divisions where the project specification requires them. Compartmentation can allow part of the storage system to remain available while another section is isolated for inspection, cleaning or maintenance, subject to the hydraulic design of the system.

Adequate clearance should be allowed for installation, inspection, cleaning and future maintenance. The exact requirement depends on the tank configuration, access arrangement and manufacturer’s installation guidance. This should be reviewed during the design stage rather than after the plant room layout has been finalised.

Hospital water storage design should consider required capacity, peak demand, resilience, access for maintenance, water turnover, hygiene controls, available plant-room space and the applicable healthcare guidance. The tank itself is only one part of the wider water system, so pipework, distribution, maintenance access and operational continuity also need to be considered.

About University Hospital Crosshouse

University Hospital Crosshouse is a large district general hospital near Kilmarnock operated by NHS Ayrshire & Arran. The hospital provides a wide range of services and is home to the national Cochlear Implant Service. Its Emergency Department serves East and North Ayrshire, and the hospital also provides paediatric inpatient services.

ABOUT TRICEL WATER

Tricel Water manufactures GRP cold water storage tanks for healthcare, commercial, infrastructure and industrial applications across the UK and Ireland.
Its sectional water storage tanks are designed for applications where access, capacity, water quality and installation conditions require a configurable storage system. Tricel Water supports projects from tank specification and manufacture through to installation and aftercare.
For healthcare applications, Tricel currently states that its sectional tanks are manufactured to BS EN 13280 and that its potable-water products have third-party certification for Regulation 4 water-contact requirements.

CONTENTS

Explore Further

Guides, Standards & Resources

Every Tricel Water project draws on the same technical foundation. Use the resources below to see more real-world installations, check design and compliance detail, and download the documentation you need for your own specification.

sizing

Case Studies

Browse real installations across education, infrastructure, healthcare, high-rise and fire protection projects to see how our tanks solve site-specific challenges.

System design

Technical Guides

Step-by-step guidance on tank sizing, installation, cleaning & disinfection, and break tank & booster set design, written for engineers and site teams.

Compliance

Specification Guides

Ready-to-use clauses and design parameters for architects, consulting engineers and MEP contractors writing tanks into a project specification.

Commissioning

Standards & Compliance

Understand the regulations behind every installation, including BS EN 13280, the Water Supply (Water Fittings) Regulations, confined space and Legionella guidance.

Regulations

Certifications

Understand the regulations behind every installation, including BS EN 13280, the Water Supply (Water Fittings) Regulations, confined space and Legionella guidance.

Safety

Product Brochures

Download detailed brochures covering our sectional, one-piece, sprinkler and combined tank & pump station ranges to support your project planning.

The details in this case study were correct at the time of publishing and are provided as general guidance and for informational purposes only. They do not constitute engineering advice and should not be relied upon as the sole basis for design decisions. Always consult a qualified engineer and verify current specifications, standards and regulatory requirements before proceeding with your own project. © 2026 Tricel Water. All rights reserved.